To make sure Parsons Contractors possess the same level of commitment to worker safety as Parsons, all Contractors are required to complete the Parsons online Global CSE Program prior to working on a project, and to update their information at the beginning of each year. After completion, the company information is saved in a database for consideration on all Parsons projects for the duration of the calendar year.
Below are minimum insurance limits required of vendors, subcontractors, and subconsultants engaged in work on the Faro Mine Remediation Project (FMRP).
Under some work packages, coverages may need to be higher based on the particulars of that package’s scope.
The purpose of the Project specific EPP is to ensure adherence to the Faro Mine Remediation Project (FMRP) Environmental Management Plan (EMP). Through the development of project specific EPPs it allows the “constructor” to develop their project in alignment with the FMRP EMP. The FMRP EMP ensures that the activities are being developed in accordance with federal and territorial regulations and legislation.
Use the EPP is to describe the environmental protection measures that will be implemented by your Company during the Project. The content of the EPP is based the environmental sensitivities and environmental protection requirements described in the Government of Canada’s Environmental Management Plan.
Implementing environmental protection measures identified within the EPP.
Training and educating crews to be aware of environmental sensitivities and how to best implement the protection measures.
Issuing stop-work orders if unknown or unanticipated environmental hazards or work conditions evolve and develop strategies to mitigate or eliminate them.
Communicating with Main Construction Manager (MCM) related to the environmental protection measures at the site about any issues or concerns.
Maintaining records and documents in accordance with the EPP, individual environmental monitoring plans, and project specifications.
Completed Map(s) provided for location of disturbance.
Submitted/Approved Sediment and Erosion Control Plan
Required if area being disturbed is within 30 m of a waterbody.
Required if disturbed area and/or remaining stockpiles are in a location with significant human activity and is likely to result in dust dispersion.
Subcontractors must submit a notice of work to Parsons prior to conducting field work. The notice of work will include items such as:
Section
|
Information Required
|
Section
|
Information Required
|
||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
1
|
Health, and Environmental Policy Statement
|
11
|
Integration of SH&E Risk Mitigation Planning in 2-Week Look-ahead Submissions
|
||||||||
2
|
Scope of Work Evaluation
|
12
|
Employee Participation and Consultation
|
||||||||
3
|
Responsibility and Identification of Key Personnel
|
13
|
Emergency Action Plan
|
||||||||
4
|
Overall Assessment of SH&E Hazards, Exposures, and Risks
|
14
|
Site-specific Medical Emergency Plan
|
||||||||
5
|
Relevant SH&E Compliance Programs, Associated Compliance Information, and Personnel Responsibility Assignments
|
15
|
Incident Reporting, Investigation, and Corrective Action Processes
|
||||||||
6
|
SH&E Compliance Training Matrix and Training / Education Processes
|
16
|
Work Site Inspection and Program Audit Processes
|
||||||||
7
|
Site-specific Worker Orientation Program
|
17
|
Progressive Disciplinary Program
|
||||||||
8
|
Identification of Competent / Qualified Personnel
|
18
|
Recordkeeping / Document Retention Processes
|
||||||||
9
|
Hazard Identification, Notification, and Correction Process
|
19
|
Other (as defined by Contractor or Parsons)
|
||||||||
10
|
Specific Hazard and Risk Control Measures (e.g., Activity Hazard Analyses, Operational Risk Management Processes)
|
20
|
Other (as defined by Contractor or Parsons)
|
Item
|
Description
|
Completed (Y/N)
|
|||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
1
|
Register online with Parsons Global Contractor Safety Evaluation (CSE)
|
|
|||||||||
2
|
All Online CSE Questions Answered & Documents Uploaded
|
|
|||||||||
3
|
Contacted FMC H&S For Any Queries Before Pressing "Submit" Tab In The CSE
|
|
|||||||||
4
|
Pressed The " Submit" Tab In The CSE Online System
|
|
|||||||||
5
|
Provided FMC H&S With a Letter Stating the Scope of Work (include in SSHEP)
|
|
|||||||||
6
|
All Staff Have Reviewed, Signed the FMC EMP And Submitted to FMC H&S
|
|
|||||||||
7
|
The SSHEP is Created, Reviewed and Signed by All Employees & Sent to FMC H&S
|
|
|||||||||
8
|
*General Liability Insurance Certificate to FMC H&S (or as part of contract award)
|
|
|||||||||
9
|
*Insurance For All Company Owned Vehicles to Be Used on Site Sent to FMC H&S
|
|
|||||||||
10
|
Required Safety Certs. /Licenses Sent to FMC H&S (i.e., Bucket truck/Fall Protection, et al.)
|
|
|||||||||
11
|
YWCHSB Clearance Letter Sent to FMC H&S
|
|
|||||||||
12
|
Provided List of Inbound Personnel to FMC H&S (Min. 2 Days in Advance of Arrival)
|
|
|||||||||
13
|
Copies Of Driver Licenses of On-Site Driving Personnel Sent to FMC H&S
|
|
|||||||||
14
|
**Communicated To All Inbound Employees of Site Safety Orientation Days/Times**
|
|
|||||||||
15
|
Received Written Approval Your Company Has Met Parsons H&S Requirements
|
|